Completion of the section that will connect Pyrzowice with Czestochowa is due by the end of 2018.
It is the first of four contracts signed for construction of the motorway. Strabag’s offer is believed to be around €144 million, while the budget set by the General Directorate for National Roads and Motorways (
Meanwhile, the S6 dual carriageway construction contract has gone to Przedsiebiorstwo Robot Mostowych.
The deal for a section between Goleniow and Koszalin is estimated to be worth more than €92.2 million, well below the €152 million budget set by the GDDKiA, according to media reports.